I'm trying to reduce the duration of a child task to bring the finish date forward. It worked for the child task. But the parent task finish date is not getting changed. All are auto scheduled. Can you please help.
Before the change :
| Task Name | Duration | Baseline Start | Baseline Finish | Start | Finish | Actual Start | Actual Finish | % Complete | Predecessors |
| APAC (Outplacement) | 181 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 1/5/15 | Mon 4/28/14 | NA | 50% | |
| Finalize Outplacement vendors | 146 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | NA | 95% | 4FS+20 days |
| Career Center Services Begin with Open House/Orientation Sessions | 146 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | NA | 50% | 4FS+20 days |
| 1:1 on-site supporting begins - MS focused support | 146 days | Mon 4/28/14 | Mon 11/17/14 | Mon 6/16/14 | Mon 1/5/15 | Mon 6/16/14 | NA | 66% | 4FS+20 days |
| Career Enhancement Office Opens | 146 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | NA | 75% | 4FS+20 days |
| Cargill Weekly Utilization and Placement Reviews | 146 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | NA | 78% | 4FS+20 days |
| On-site job fair | 146 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | NA | 80% | 4FS+20 days |
After the change :
| Task Name | Duration | Baseline Start | Baseline Finish | Start | Finish | Actual Start | Actual Finish | % Complete | Predecessors |
| APAC (Outplacement) | 181 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 1/5/15 | Mon 4/28/14 | NA | 50% | |
| Finalize Outplacement vendors | 146 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | NA | 95% | 4FS+20 days |
| Career Center Services Begin with Open House/Orientation Sessions | 146 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | NA | 50% | 4FS+20 days |
| 1:1 on-site supporting begins - MS focused support | 120 days | Mon 4/28/14 | Mon 11/17/14 | Mon 6/16/14 | Fri 11/28/14 | Mon 6/16/14 | NA | 80% | 4FS+20 days |
| Career Enhancement Office Opens | 146 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | NA | 75% | 4FS+20 days |
| Cargill Weekly Utilization and Placement Reviews | 146 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | NA | 78% | 4FS+20 days |
| On-site job fair | 146 days | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | Mon 11/17/14 | Mon 4/28/14 | NA | 80% | 4FS+20 days |